Section of bullet train project faces a further 2-year delay, contractor warns

A major construction team on the California bullet train project notified the state rail authority this month that it will not complete a 65-mile section of the future route in Kings County until at least April 14, 2025 — nearly two years after the date that the state included in a business plan adopted Thursday.

The additional delay could again boost costs and jeopardize the state’s funding plan to complete a partial operating system between Bakersfield and Merced by 2030. The project’s rising price tag has forced the state to repeatedly scale it back and delay indefinitely a goal to have the train running from Los Angeles to San Francisco — at speeds up to 220 miles per hour — by 2020.


The notification of the new delay came in a letter dated March 9 to the California High-Speed Rail Authority. A construction team led by the Spanish firm Dragados described a chaotic system for projecting future construction progress because of state delays in securing land for construction.

The Times obtained a copy of the letter, which complained that the rail authority’s failure to accurately predict land acquisition has tangled construction schedules and caused fitful conditions along the route.

Read the full story on LATimes.com.